Construction Progress

Follow the journey of this construction project.

Our Construction Progress page provides a detailed overview

of the work completed month by month.

From initial site preparation to the final coat of paint. 

 

MONTH ( 2025 ) EVENT PERCENTAGE OF PROGRESS
JUNE 30 Tree Protections 100%
JUNE 17 Septic Tank Abandonment 100%
JULY 16 Temporary Fence Installation 100%
JULY 14 Gravel Installation 100%
JULY 25 Demolition of Existing House 100%
AUGUST 14 Debris Removal 100%
SEPTEMBER 9 Tree Removal 100%
SEPTEMBER 4 Record a Notice of Commencement 100%
SEPTEMBER 1 Open utilities account for temporary electrical 100%
OCTOBER Open utilities account for temporary Water 0%
OCTOBER 6 Delivery of Portable Toilet 100%
OCTOBER 5 Survey to mark set backs and reference points 30%
--- Start Excavations for Structural Footing Work
--- Structural Foundation Work
--- Pouring Footing's concrete
--- Start installation of concrete masonry units around building
--- 1st backfill to reach desire elevation
--- Underground work. Mechanical, Electrical and Plumbing
--- 2nd backfill
--- Preparation for concrete slab @ Ground Level.
--- Pouring concrete slab @ Ground Level
--- Continuing Installation of CMU in exterior walls from ground floor to tie beams intermidiate level
--- Preparation for Concrete Slab @ Second Floor Level. Includes forms, rebars, braces, etc
--- Installation of necessary conduits, pipes, etc for utilities to be running insde conrcete at second level. Mechanical, Electrical and plumbing
--- Pour concrete slab at second floor level
--- Installation of CMU from concrete slab second level to roof level. Includes installation of tie beams, tie columns, steel columns
--- Preparation for concrete slab @ Roof Level. Includes installation of forms, rebars
--- Installation of necessary conduits, pipes, etc for utilities to be running insde conrcete at second level. Mechanical, Electrical and plumbing
Pour concrete slab at roof level
Start Exterior Stucco Work in walls. Includes placing scaffolding system
Excavation for new Septic Tank and Drainfield Area. Installation of new Septic Tank

Create Your Own Website With Webador