Construction Progress

Follow the journey of this construction project.

Our Construction Progress page provides a detailed overview

of the work completed month by month.

From initial site preparation to the final coat of paint. 

 

MONTH ( 2025 ) EVENT PERCENTAGE OF PROGRESS
JUNE 30 Tree Protections 100%
JUNE 17 Septic Tank Abandonment 100%
JULY 16 Temporary Fence Installation 100%
JULY 14 Gravel Installation 100%
JULY 25 Demolition of Existing House 100%
AUGUST 14 Debris Removal 100%
SEPTEMBER 9 Tree Removal 100%
SEPTEMBER 4 Record a Notice of Commencement 100%
SEPTEMBER 1 Open utilities account for temporary electrical 100%
---- Open utilities account for temporary Water N/A (Well water on site)
OCTOBER 6 Delivery of Portable Toilet 100%
OCTOBER 5 Survey to mark set backs and reference points 100%
NOV 3 Start Excavations for Structural Footing Work 100%
NOV 10 Structural Foundation Work 100%
NOV 15 Pouring Footing's concrete 100%
NOV 21 Start installation of concrete masonry units around building 100%
DEC 2 1st backfill to reach desire elevation 100%
DEC 15 Underground work. Mechanical, Electrical and Plumbing 100%
DEC 22 2nd backfill 100%
DEC 26 Preparation for concrete slab @ Ground Level. 100%
DEC 29 Pouring concrete slab @ Ground Level 100%
********** MONTH ( 2026 ) ******** *************** EVENT ************** ***** PERCENTAGE OF PROGRESS *****
JAN 15 Continuing Installation of CMU in exterior walls from ground floor to tie beams intermidiate level 100%
JAN 30 Preparation for Concrete Slab @ Second Floor Level. Includes forms, rebars, braces, etc 80%
--- Installation of necessary conduits, pipes, etc for utilities to be running insde conrcete at second level. Mechanical, Electrical and plumbing
--- Pour concrete slab at second floor level
--- Installation of CMU from concrete slab second level to roof level. Includes installation of tie beams, tie columns, steel columns
--- Preparation for concrete slab @ Roof Level. Includes installation of forms, rebars
--- Installation of necessary conduits, pipes, etc for utilities to be running insde conrcete at second level. Mechanical, Electrical and plumbing
Pour concrete slab at roof level
Start Exterior Stucco Work in walls. Includes placing scaffolding system
Excavation for new Septic Tank and Drainfield Area. Installation of new Septic Tank
Start waterproofing work at roof level
Installation of roof system as per plans.
Start Interior Framing Metal Installation
Installation of interior metal stair
Rough Installation Mechanical, Electrical and Plumbing
Installation Impact Doors and Windows
Hanging Drywall
Start Smooth finish in walls
Start interior primer paint
Start flooring installation at first level and in bathrooms at second level. Includes walls tiles
Installation of Guard rails as needed in Staris, balconies and openings
Millwork. Installation Kitchen Cabinets, Vanities, Closets, Interior Doors, Baseboards
Finishes Mechanical, Electrical and Plumbing
Exterior Aluminum Work. Installation of exterior fence, louvers
Installation of underground propane gas tank
Installation of Generator
Final two coat Interior paint
Final Two Coat Exterior Paint
Final Mechanical, Electrical and Plumbing Inspection
Final Zoning Inspection
Final Inspection Fire Department
Final Building Inspection
Touch up and Final details
********************************